The Midland Main Line (MML), a major railway line in the United Kingdom, has been undergoing various upgrades since 2015.[1] The current programme of upgrades began in 2012, although electrification was proposed a number of times previously.[2] The current programme includes electrification of the railway line between Bedford, Wellingborough, Corby, Leicester, Derby, Nottingham and Sheffield. The routes between Nottingham and Sheffield and the Erewash Valley line were not included at this time, only the line between Derby and Sheffield. The upgrade was part of the HLOS (High Level Output Specification) for Control Period 5 published by the UK Government in 2012.[3]
To enable all the benefits of using electric traction, the line from Bedford to St Pancras is also being upgraded which includes boosting the power supply.[4][5] Parts of the line have been classed as congested infrastructure hence another reason for the upgrade.[6]
The upgrading of the overhead line equipment (OLE) south of Bedford is underway to allow 125 mph (201 km/h) running and due for completion in late 2025.[5] The Kettering to South Wigston stretch was energised in July 2024.
Background
The commuter route at the southern end of the line between London St Pancras and Bedford, nicknamed the Bedpan line, was electrified with overhead line in the early 1980s and completed in 1983.[7] This section is mainly a commuter route. It was the subject of an industrial dispute when driver-only operation (DOO) electric trains were introduced.[8]
As the line is a key strategic artery and a radial main line originating in London, there have been many calls for it to be electrified, especially now that the Great Western Main Line and East Coast Main Line are electrified, along with the West Coast Main Line which was electrified in the 1960s and 1970s. The desire to achieve net zero carbon in transport has increased calls for the line to be electrified/decarbonised. There is also the desire to increase some sections of the line to 125 mph (201 km/h) speed capability.[9]
History and earlier proposals
In the 1970s large scale electrification was proposed on the back of the West Coast Main Line electrification and partially in response to the oil crisis of that decade.[10] In 1981 the British Railways Board published a final document on railway electrification that included the Midland Main Line as high priority.[11] In the intervening years priority was put on other projects such as schemes in Anglia and the East Coast Main Line.[12] Then in the 1990s, British Rail was privatised followed by a change in government.[13]
21st century proposals
In July 2009, the Labour government published a document and said it was looking at electrification of the Midland Main Line, but no funds had been committed.[14] When originally planned and announced in the 21st Century, the line upgrade was costed at £1.6 billion and it was expected that the line would be electrified as far as Kettering and Corby by 2017. It was then expected that the electrification of the line would continue from Kettering to Leicester, Derby and Nottingham and would occur by 2019 and then the Sheffield section by 2020. Again only the Derby to Sheffield section of the line was planned for electrification and not the Nottingham to Sheffield route, or the through route bypassing both Derby and Nottingham – the Erewash Valley line. In addition an extra track was to be installed between Kettering and Corby to enhance capacity.[15] It appeared in the autumn statement of 2011.[16]
A 2014 article in RAIL Magazine gave a detailed account of the work that lay ahead. Rebuilding of bridges between Bedford and Leicester had already been in progress for a while. Equipment for placing the various electrification tasks such as bases and overhead line equipment was scheduled to start April 2015. The completion date for electric trains arriving at Sheffield Midland station was cited as December 2020 – the cost given as £1.3 billion pounds and also included three station modifications at Leicester, Derby and Sheffield. 422 single track miles (675 km) of wiring was supposed to occur and a total of 120 bridges modified. Bradway tunnel had already had some heavy maintenance.[17] It was further pointed out that ECAM had been used (as in the project had been through this procedure)- a term the treasury used meaning Enhancements Cost Adjustment Mechanism. Pre-ECAM the cost had been quoted at £900 million. The whole MML scheme also overlapped with the Electric Spine project.[18]
In June 2015, the Secretary of State for Transport Patrick McLoughlin informed Parliament the electrification project was being paused, resulting in criticism from local MPs. Mcloughlin said "'better services' could be delivered on Midland Mainline before electrification was completed".[19] He blamed "Network Rail for rising costs and missed targets".[19]Lilian Greenwood who at the time was Shadow Transport Secretary, and also an MP for Nottingham South, accused the government of being cynical and that they had delayed this announcement until after the 2015 United Kingdom general election which took place the previous month.[20] There were also complaints that money had been wasted on civil engineering interventions that were no longer needed.[21]
On 30 September 2015 McLoughlin restarted the scheme.[22] The new expected completion dates were now three years later than originally planned, with electrification to Kettering and Corby now targeted for completion in 2019 and then to Leicester, Derby, Nottingham and Sheffield by 2023.[23] The line from Kettering to Corby was to be doubled, and indeed Network Rail began work in June 2015.[24] The Enhancements plan update of January 2016 showed the project
on target.[25] On 27 July 2017, a further briefing paper was issued and the Midland Main Line had a section of its own.[26] This document, and the subsequent announcement by the new Secretary of State for Transport Chris Grayling said the electrification scheme north of Kettering to Derby, Nottingham and Sheffield had been cancelled and that bi-mode trains would be used.[27]
2020 and onwards timeframe
Local news outlets reported in December 2020 that electrification to Market Harborough was moving closer.[28] In February 2021, Network Rail put out a document confirming this saying that devegetation, ecological and biodiversity work was starting on the section between Kettering and north to Market Harborough as a prelude to electrification. They further stated that detailed assessment had already taken place and that this immediate ground clearance would end April 2021.[29] Local news outlets reported this work earlier but they further confirmed it.[30] There will be overlap with some Sub-national transport body such as East Midlands Connect. On 23 March 2021, the Transport Select Committee published its sixth report in the Trains fit for the Future ongoing enquiry, which called for a rolling programme of electrification.[31][32] It reported that the Midland Main Line was actively being looked at and that the project plans would be broken up into eight route sections.[33] It was reported and confirmed in Modern Railways that the contractor SPL Powerlines was working in conjunction with Network Rail to progress the project north of Market Harborough all the way to Sheffield and Nottingham and that current plans were the route would be divided into eight discrete sections.[34] It was announced that due consideration was being given to environmental protection during the upgrade with Great crested newts being given special mention.[35] On completion of certain parts of the project, environmental aspects and Green credentials were touted.[36]
In September 2020 the TDNS (Traction Decarbonisation Network Strategy) was published. Further electrification was recommended and included the Midland Main Line and fill ins such as Sheffield northwards and Birmingham to Derby. In October 2022 it was reported the TDNS had been quietly abandoned.[37]
A meeting took place in July 2021 to discuss bidding for extension of the upgrade and electrification of the line from Market Harborough to Sheffield a key stage in the project going ahead. The work would go out to tender in September 2022.[38]
On 18 November 2021, the Integrated Rail Plan (IRP) was published. This affected parts of the HS2 programme including curtailing much of the eastern leg but did include full Midland Main Line electrification and upgrades.[39]
On 21 December 2021 the DfT officially announced that work would start on 24 December 2021 on electrification of the section of line between Kettering and Market Harborough.[40][41][42]Grant Shapps controversially claimed this work was proof the IRP was being implemented quickly.[43]
On 24 May 2022 in an article in New Civil Engineer, it was announced that delivery was already in progress from Kettering to Wigston and given the section name RS1 (Route Section 1 – sometimes also referred to as K2W). Contractors were invited to a market engagement event on 15 June 2022 for the remaining sections to allow bimode trains to run on electric power all the way to Sheffield.[44] These sections for continued work were outlined. RS is a Route Section.[45]
In the August 2022 edition of Modern Railways, Roger Ford stated that RS3 will have high priority because of the diversionary route capabilities it brings.[46] The whole project has an advantage in that it is not driven by a timetable change.[47] The eight route sections are:[48][49][50][51]
RS1 – Kettering to Wigston South (includes Market Harborough and Braybrooke grid feeder).
RS2 – Wigston South to Syston (some evidence this section may have been split into 2a and 2b).[52][9]
RS3 – Syston to Trent Junction.
RS4 – Sheet Stores Junction to Chaddesden Sidings (Derby).
RS5 – Trent Junction to Nottingham.
RS6 – Chaddesden Sidings (Derby) to Toadmoor Tunnel.
RS7 – Toadmoor Tunnel to London Road.
RS8 – London Road to Sheffield North.
The September 2022 Mini-Budget, included RS3 as one of a list of infrastructure "projects to have particularly high potential to move to construction at an accelerated pace".[53][54]
October 2023 saw the publishing of the command document Network North. This document further proposed extension of the electrification of the MML from Sheffield to Doncaster and Leeds.[55]
The installation of the foundations was fully completed as of 28 November 2023 on the section of line from Kettering to Wigston and was energised on 28 July 2024.[56][57]
On 6 April 2024, the West Bridgford Wire stated that the government is committed to electrify the line to Nottingham by 2030, with the rest of the electrification to Sheffield to be done by the early 2030s due to the fact it has been going at a 'snails pace'. It also stated that the work south of Bedford is to be delivered in 2025.[58] In September 2024 there was further confirmation that planning and site investigations were ongoing for electrification to Nottingham and Sheffield.[59]
Power supply and civils
The electrified line will be fed via the autotransformer system. To cope with the higher electricity usage south of Bedford into St Pancras, the upgrade involves boosting the existing power supplies.[60] This contract has been awarded to SPL Powerlines.[61] In addition, a new grid feeder was installed at Braybrooke, just south of Market Harborough.[62] At the north end of the scheme it was proposed that a grid feeder would be located in the Chesterfield area. The middle section of the upgrade scheme would have the grid feeder located in the Kegworth area. Work was announced as starting on the grid feeder in the Market Harborough area on 8 April 2021.[63] The transformers were delivered to the site in December 2021.[64] There are a number of bridges requiring work.[65]
Wellingborough aggregates terminal
Wellingborough aggregates terminal is a rail freight terminal in Wellingborough in North Northamptonshire, adjacent to the Midland Main Line.[66] In 2022, the terminal was the site of an electrification trial. As freight trains are usually top loaded, it is not possible to install typical overhead lines. A new moveable overhead conductor was installed which retracts to allow loading of the train.[67][68]
November 2011 – autumn statement includes electrification of the line
September 2015 – electrification paused by the Secretary of State shortly after publication of the Hendy review
October 2015 – electrification unpaused but timeline for completion is delayed
July 2019 – (RSSB) Rail Industry Decarbonisation Task Force report published
April 2021 – work on Braybrooke grid feeder started.[70]
17 May 2021 – electric service from London to Corby starts.[71]
18 November 2021 – IRP published stating electrification of the whole line would take place.
21 December 2021 – official announcement and press release that Kettering to Market Harborough electrification is approved and works began from starting 24 December 2021.[69]
24 May 2022 – confirmation that contracts had been let and delivery was in progress all the way to Wigston South Junction
1 July 2022 – confirmation that work was starting on RS1 Market Harborough to South Wigston[72]
23 September 2022 – MML phase 3 listed as one of the "infrastructure projects which will be accelerated as fast as possible" in the September 2022 Mini-Budget
9 January 2023 – further bridge raising on RS2 section commencing from 13 January 2023.[73][74]
28 February 2023 – announcement that contractors were being sought for the entire route from South Wigston to Nottingham and Sheffield and design approved in principle.[75]
6 October 2023 – an invitation to tender (market interest) for the remaining sections including Nottingham and Sheffield was issued.[76] Passenger input was sought for the remaining sections and the feedback was that bus substitution was the least desirable option with more notice and longer closures along with rail diversions preferred.[77]
28 November 2023 – Foundations installation complete Kettering to South Wigston.[78]
6 April 2024 – A news article stated that the government is committed to electrify the line to Nottingham and Sheffield by 2030 and early 2030s respectively.[58]
28 July 2024 – RS1 Kettering to Wigston energised.[57][79][80]
^"HLOS CP5"(PDF). Archived(PDF) from the original on 24 December 2021. Retrieved 19 February 2021.
^Sherratt, ed. (June 2023). "125mph upgrade for MML OLE south of Bedford". Modern Railways. Vol. 80, no. 897. Key Publishing. pp. 22–23. ISSN0026-8356.
^ abFPWI, Peter Stanton BSc CEng FIMechE FIET (19 December 2023). "Sparking the Midlands". Rail Engineer. Archived from the original on 22 December 2023. Retrieved 22 December 2023.
^"British Rail: the timescale for a strategic electrification programme". Modern Railways. Vol. November 1974. November 1974 – via Ian Allan publishing.
^"Rail Electrification"(PDF). July 2009. Archived from the original on 5 August 2009. Retrieved 22 February 2021.{{cite web}}: CS1 maint: bot: original URL status unknown (link)
^"Autumn Statement 2011"(PDF). UK Government. 2011. Archived from the original on 1 April 2014. Retrieved 5 March 2021.{{cite web}}: CS1 maint: bot: original URL status unknown (link)
^ abFord, Roger (August 2021). "Informed Sources Table 1:Electrification Policy Timeline". Modern Railways. September 2021: 32–33 – via Key Publishing.
^"East Midlands Railway reveals the interior looks of its new Aurora train fleet". News. Railways Illustrated. No. 254. April 2024. p. 7.
Further reading
Wolmar, Christian (2005). On the Wrong Line: How Ideology and Incompetence Wrecked Britain's Railways (rev. ed.). London: Aurum Press. ISBN1-85410-998-7.
Nock, O.S. (1965). Britain's new railway: Electrification of the London-Midland main lines from Euston to Birmingham, Stoke-on-Trent, Crewe, Liverpool and Manchester. London: Ian Allan. OCLC59003738.
"On board with electrification". Permanent Way Institution Journal. 139 (1). January 2021. ISSN2057-2425 – via PWI.
Nock, O.S. (1974). Electric Euston to Glasgow. Ian Allan. ISBN978-0711005303.
Keenor, Garry. Overhead Line Electrification for Railways.
Boocock, Colin (1991). East Coast Electrification. Ian Allan. ISBN0-7110-1979-7.
Semmens, P.W.B. (March 1991). Electrifying the East Coast Route: Making of Britain's First 140m.p.h. Railway. Patrick Stephens Ltd. ISBN978-0850599299.
Tom VilsackNama dalam bahasa asli(en) Tom Vilsack BiografiKelahiran13 Desember 1950 (72 tahun)Pittsburgh 32è Daftar Menteri Pertanian Amerika Serikat 24 Februari 2021 – ← Sonny Perdue 30è Daftar Menteri Pertanian Amerika Serikat 21 Januari 2009 – 13 Januari 2017 ← Ed Schafer 40è Governor of Iowa (en) 15 Januari 1999 – 12 Januari 2007 ← Terry Branstad – Chet Culver → ...
Эта статья — о научно-популярном сериале BBC. Об аниматронном шоу см. Прогулки с динозаврами (аниматронное шоу). Прогулки с динозаврамиангл. Walking with Dinosaurs Обложка DVD-издания от «Союз-Видео» Жанр научно-популярный фильм Создатель Тим Хэйнс (англ.) (рус. Сце
Активистки четвёртой волны феминизма, Лондон, 2017 Четвёртая волна феминизма — это ветвь феминистского движения, отделившаяся около 2012 года, которая делает акцент на расширении прав и возможностей женщин[en][1], использовании интернет-инструментов[2] и интерсек
Cosetta GrecoGreco pada 1954Lahir(1930-10-08)8 Oktober 1930Trento, ItaliaMeninggal14 Juli 2002(2002-07-14) (umur 71)Roma, ItaliaPekerjaanPemeranTahun aktif1943–1971 Cosetta Greco (8 Oktober 1930 – 14 Juli 2002) adalah seorang pemeran film Italia. Ia tampil dalam 31 film antara 1943 dan 1971.[1] Filmografi pilihan Addio, amore! (1943) Caccia all'uomo (1948) The Charterhouse of Parma (1948) The Bride Can't Wait (1949) Four Ways Out (1951) The Cape of Hope (19...
Dit artikel gaat over het eiland van de archipel. Zie Tristão da Cunha voor de ontdekkingsreiziger. Tristan da Cunha Eiland van Vlag van Verenigd Koninkrijk Sint-Helena, Ascension en Tristan da Cunha (Details) (Details) Locatie Land Vlag van Verenigd Koninkrijk Sint-Helena, Ascension en Tristan da Cunha Locatie Atlantische Oceaan Coördinaten 37° 8′ ZB, 12° 17′ WL Algemeen Oppervlakte 98 km² Inwoners (2018) 254 (1,4/km2) Hoofdplaats Edinburgh-of-the-Seven-Seas Lengte...
World War II atrocity Hurby massacreHurbyŁuckBrześćLwówKrakówPoznańWarsawWilnoStanisławówclass=notpageimage| Location of the Massacre (map of the Second Polish Republic from before the German-Soviet invasion of 1939)DateJune 2, 1943LocationHurby village, German-occupied Poland, present-day location in UkraineTypeCivilian massacreMotiveAnti-Catholicism, Anti-Polish sentiment, Greater Ukraine, UkrainisationParticipantsUkrainian Insurgent Army, CKBDeathsc. 250 Hurby massacre was a mass m...
GD & TOPInformasi latar belakangAsalSeoul, Korea SelatanGenreK-pop, hip hopTahun aktif2010 (2010)—kiniLabelYG EntertainmentArtis terkaitBIGBANGAnggota G-Dragon T.O.P GD & TOP adalah duo hip hop asal Korea Selatan yang dibentuk oleh G-Dragon dan T.O.P dari grup musik Big Bang pada tahun 2010.[1] Riwayat YG Entertainment mengumumkan sub-unit G-Dragon dan T.O.P di bawah nama GD & TOP pada November 2010 dan akan merilis sebuah album dengan judul diambil dari nama duo te...
Die oströmische Provinzeinteilung Ägyptens um 400 n. Chr. Später kamen durch Teilungen zwei weitere Provinzen hinzu (Augustamnica II und Thebais II). Die byzantinische Zeit begann in Ägypten im Jahr 395 mit der Aufteilung des Römischen Reichs, wonach Ägypten zum Ostreich (Byzanz) gehörte. Sie kann ebenso gut als bruchlose Fortsetzung bzw. zweiter Abschnitt der spätantiken griechisch-römischen Phase des Landes verstanden werden und endete mit der Eroberung des Landes durch die Araber ...
Artikel ini sebatang kara, artinya tidak ada artikel lain yang memiliki pranala balik ke halaman ini.Bantulah menambah pranala ke artikel ini dari artikel yang berhubungan atau coba peralatan pencari pranala.Tag ini diberikan pada November 2022. Hanna SturmLahirJohanna Sturm28 Februari 1891Klingenbach, Eisenstadt, Austria-HungariaMeninggal9 Maret 1984Zagreb, Republik Sosialis Kroasia, Republik Federal Sosialis YugoslaviaPekerjaanserikat pekerja dan aktivis politikaktivis perdamaianDikenal ata...
يو-237 الجنسية ألمانيا النازية الشركة الصانعة فريدريش كروب المالك كريغسمارينه المشغل كريغسمارينه (30 يناير 1943–4 أبريل 1945)[1] المشغلون الحاليون وسيط property غير متوفر. المشغلون السابقون وسيط property غير متوفر. التكلفة وسيط property غير متوفر. منظومة التعاريف الاَلية لل...
CanadaAssociationVolleyball CanadaConfederationNORCECAHead coachTuomas SammelvuoFIVB ranking12 (as of 2 December 2023)Uniforms Home Away Third Summer OlympicsAppearances5 (First in 1976)Best result4th (1984)World ChampionshipAppearances12 (First in 1974)Best result7th (2014)World CupAppearances5 (First in 1977)Best result7th (2003, 2015)NORCECA ChampionshipAppearances28 (First in 1969)Best result (2015)Volleyball.ca Honours World League 2017 Curitiba NORCECA Championship 2015 Córdoba 1979 Ha...
Character group from J. R. R. Tolkien's legendarium Dark Riders and Black Riders redirect here. For other uses, see Dark Rider (disambiguation), Black Rider (disambiguation), and Nazgul (disambiguation). Fictional character NazgûlIn-universe informationAliasesThe NineÚlairi (in Quenya)Black RidersFell RidersRingwraithsBook(s)The Fellowship of the Ring (1954),The Two Towers (1954),The Return of the King (1955),The Silmarillion (1977),Unfinished Tales (1980) The Nazgûl (from Black Speech naz...
City in Alabama, United States City in Alabama, United StatesAuburn, AlabamaCityCity of AuburnCampus of Auburn University, downtown Auburn, one of Auburn's many biking and walking trails, and Auburn City Hall. FlagSealMotto: The Loveliest Village On The PlainsLocation of Auburn in Lee County, Alabama.AuburnCoordinates: 32°35′52″N 85°28′51″W / 32.59778°N 85.48083°W / 32.59778; -85.48083CountryUnited StatesStateAlabamaCountyLeeFounded1836IncorporatedFebr...
Turkey's blockage of access to Wikipedia, 2017–2020 The Turkish Wikipedia logo with a censor bar covering the text The logo displayed after the two-year anniversary of the ban, with the message 2 yıldır özlüyoruz (English: we've been missing it for two years) A graph of page views for the Turkish Wikipedia from February to May 2017 shows a great drop of roughly 80% immediately after the block was imposed. With Wikipedia's content being open, alternative websites continued to provide the...
This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: Zero Tolerance 1999 film – news · newspapers · books · scholar · JSTOR (June 2021) (Learn how and when to remove this template message) 1999 Swedish filmZero ToleranceDVD coverDirected byAnders NilssonWritten byAnders NilssonJoakim HanssonProduced byBjörn...
Carlsberg and Tuborg signs in Fredericia The beer market in Denmark is dominated by the brands Carlsberg and Tuborg. Since Tuborg was acquired by Carlsberg in 1970, Carlsberg has held a near-monopoly. A number of regional breweries, however, managed to survive, and most of them merged into Royal Unibrew in 2005. As of 2020, Ratebeer lists over 300 active breweries in Denmark, most of which are microbreweries.[1] Economy The Danish market is dominated by pale lager, with more than 95% ...
2019 video game Sonic Racing redirects here. For other Sonic racing games, see List of Sonic the Hedgehog video games § Racing games. 2019 video gameTeam Sonic RacingDeveloper(s)Sumo DigitalPublisher(s)SegaDirector(s)Shunsuke KawarazukaProducer(s)Takashi IizukaDesigner(s)Derek LittlewoodRichard AcherkiProgrammer(s)Chris JacksonTim FurnishArtist(s)Kelvin TuiteCris Lonergan-WhiteComposer(s)Jun SenoueTee LopesSeriesSonic the HedgehogPlatform(s)Nintendo SwitchPlayStation 4WindowsXbox OneRel...
Kota PrabumulihKotaTranskripsi bahasa daerah • Abjad Jawiڤرابوموليه • Surat Uluꤶ꥓ꤽꤷꥈꤸꥈꤾꥇꥁ꥓Dari Atas, Kiri ke kanan: Stasiun Kereta Api Kota Prabumulih, Jalanan di Kota Prabumulih, Gerbang Perbatasan Prabumulih dengan Muara Enim LambangJulukan: Kota NanasMotto: Prabumulih jaya - Seinggok sepemunyianJayalah Kota Prabumulih - Seiya sekataPetaKota PrabumulihPetaTampilkan peta SumatraKota PrabumulihKota Prabumulih (Indonesia)Ta...
Untuk kegunaan lain, lihat Aceh (disambiguasi). Koordinat: 3°48′N 96°52′E / 3.800°N 96.867°E / 3.800; 96.867 Kabupaten Aceh Barat DayaKabupatenTranskripsi bahasa daerah • Jawoëاچيه بارات ديا LambangMotto: Sapeue kheuen sahou langkah(Aceh) Seiya sekata menyatukan langkahPetaKabupaten Aceh Barat DayaPetaTampilkan peta SumatraKabupaten Aceh Barat DayaKabupaten Aceh Barat Daya (Indonesia)Tampilkan peta IndonesiaKoordinat: 3°47′...