Share to: share facebook share twitter share wa share telegram print page

Sarawak Corridor of Renewable Energy

The logo of SCORE

The Sarawak Corridor of Renewable Energy (SCORE; Malay: Koridor Tenaga Diperbaharui Sarawak) is an economic region and development corridor covering central Sarawak, a Malaysian State on the island of Borneo. SCORE was launched in 2008. It is one of the five regional development corridors launched throughout Malaysia during the Abdullah Badawi administration.[1] SCORE is managed by the Regional Corridors Development Authority ("RECODA"), a state government agency created through an Ordinance of the State Legislative Assembly.[2][3]

History

SCORE was launched on 11 February 2008 by the 5th Malaysian Prime Minister, Datuk Seri Abdullah Ahmad Badawi.[4] SCORE was immediately placed under the jurisdiction of Regional Corridors Development Authority (RECODA) where the latter was created under an ordinance passed in the state assembly back in 2006. RECODA must consist of a chairman, two deputy chairmen, and between five and ten other board members. This agency promotes, manages, and oversees the implementation of development projects inside the corridor.[3] SCORE covered an area of 70,000 km2 at the central region of Sarawak, with a coast line of 320 km long; encompassing urban centres such as Sibu, Bintulu, Mukah, Sarikei, Bintulu, Miri, Lawas, Limbang, and Kapit.[2]

Initial plan for SCORE was to construct 12 hydroelectric dams with 7,800 MW of installed capacity, connected to industrial facilities located at the coast of Sarawak, targeting 50 dams with eventual installation capacity of 20,000 MW.[5] Batang Ai Dam was commissioned on 21 August 1985, followed by Bakun Dam in 2014,[6] and Murum Dam in 2015.[7] In November 2015, chief minister Adenan Satem halted the Baram Dam project indefinitely due to persistent protests from the local communities.[8] In 2017, Sarawak acquired Bakun Dam from the Malaysian federal government at a cost of RM 2.5 billion.[9] Baleh Dam started construction in 2020 after completion of river diversions works.[10] The dam is expected to commission in 2026.[11]

Companies given the pioneer status, involving in high tech industries, heavy capital investments, or high research and development activities will enjoy 100% exemption on its statutory income for 5 years.[12] Other incentives include Investment Tax Allowance (ITA) and Reinvestment Allowance (RA) in the manufacturing industry.[13]

In 2021, SCORE became part of the "Post Covid-19 development strategy" where the latter was introduced in July 2021.[14]

Targets

The initial aim of setting up SCORE was to develop central region of Sarawak, improving the state's economic growth, thus achieving the national objective of Vision 2020 for becoming a developed state.[2] The development corridor also targets 1.5 million jobs creation by the year 2030.[15] By 2013, the state government has identified SCORE as one of the means to achieve high income and advanced economy by 2030.[16][17] The economic corridor also planned to achieve RM 334 billion (US$110 billion) in total investments, where RM 67 billion (20%) are funded by the government[17] (a mix of investments from government-linked companies, state, and federal funds)[5] and the remaining RM 267 billion (80%) are funded by private sector.[17] Other targets include: increase the size of the economy by a factor of five to RM 118 billion, increase per capita income to RM 97,400,[18] increase the number of jobs by a factor of 2.5, and doubling the population to 4.6 million by the year of 2030.[5]

It focus on ten priority industries in agriculture, mining, and manufacturing sectors such as aquaculture, livestock rearing, timber, palm oil, petroleum, aluminum, and steel and glass industries.[2] Total investments into these industries are projected to reach RM 200 billion where oil-based industries amount to RM 60 billion, aluminium industry accounted for RM 23 billion, palm oil industry at RM 17 billion, and timber-based industry RM 11 billion.[5]

Agencies Under RECODA

Source: RECODA

In order to expand the SCORE initiative into rural Sarawak, three agencies under RECODA were established. This initiative expanded the SCORE development area from initial 70,000 km2 to 100,000 km2, which is about two-thirds of Sarawak area.[19]

Upper Rajang Development Agency (URDA)

URDA was established on July 12, 2017.[19] Its inaugural chairman was deputy chief minister James Jemut Masing.[20] This agency covers areas involving Kapit, Kanowit, Song, Belaga, and Bukit Mabong, totalling 41,186 km2 in area.[21] Major development projects for URDA are the construction and management of Bakun Dam, Murum Dam, and Baleh Dam and building access roads to the dams and between settlement areas.[22]

As of December 2020, there were four projects under planning and 28 projects under implementation. One of such projects is the construction of 73 km road network from Kapit to Baleh Dam. This enables remote villages from around Baleh area road access to Kapit town.[23]

Highland Development Agency (HDA)

HDA was established on July 12, 2017.[19] This agency covers an area of 18,462 km2 involving 75,000 people across 244 villages and longhouses in Bario, Mulu, and Long Lama.[21][24] Deputy chief minister Douglas Uggah Embas served as the inaugural chairman of the HDA.[19][20][25] As of December 2020, 10 projects were under planning and 19 projects were under implementation under HDA.[23] Among the projects implemented were Long Lama Rural Growth Centre and Integrated Highland Agriculture Station (IHAS).[26] IHAS aims to become an agricultural products collection, chilling, and packaging facility for the Baram region.[23] IHAS covers an area of 634 hectares including Long Beruang, Long Banga, and Long Peluan areas. Facilities included in IHAS are offices, an internet centre, a multipurpose hall, a production centre, schools, hostels, a training centre, and road networks connecting to surrounding farmlands.[22] In September 2022, IHAS was transferred to a new ministry named Ministry of Modernisation of Agriculture and Regional Development Sarawak (MANRED).[27]

Northern Region Development Agency (NRDA)

NRDA was established on March 15, 2018.[19] Deputy chief minister Awang Tengah Ali Hassan was the inaugural NRDA Chairman.[20] It encompasses Limbang and Lawas, covering an area of 7,790 km2.[21] NRDA is involved in roads constructions, building water supply, and a new airport in Lawas.[28] As of December 2020, 12 projects were under planning and 64 projects were under implementation. One of such projects is Northern Coastal Highway that aims to connect Miri, Limbang, and Lawas to neighbouring state of Sabah through various custom checkpoints in Brunei, Limbang, and Lawas; by constructing a dual carriageway.[23]

Growth nodes

Samalaju

Samalaju Industrial Park began construction in 2009.[29][30] In January 2011, Tokuyama's polycrystalline silicon factory was opened in the industrial park.[29] As of 2012, investors committed RM 29 billion to Samalaju Industrial Park, created 17,333 new jobs.[18] As of 2014, 15 out of 19 projects in SCORE are located in Samalaju, with total cumulative foreign direct investment (FDI) of MYR 27 billion.[31] Companies such as Press Metal Bhd, OM Materials (Sarawak), Pertama Ferroalloys, Sakura Ferroalloys, OCI Malaysia (previously Tokuyama Malaysia), and Iwatani-SIG Industrial Gases Sdn Bhd, and Elkem Carbon Malaysia are operational in Samalaju since 2014.[31][32] Other development projects near the industrial park are Samalaju Eco Park Township and Samalaju port. Residential properties, shoplots, transportation hub, and light industrial facilities are located inside the Eco Park Township. Samalaju port handled 4 million tonnes of cargo annually in 2015.[33]

As of 2018, there was no data of socioeconomic impact on the local community, such as employment and wages, and involvement of local companies in the industrial park.[34] In response to this, the 2019 RECODA annual report included details of private investments made by each company and number of jobs created.[35]

Mukah

Mukah aims to become a smart city focusing in education and information technology.[36] Amongst projects that were planned in 2013 were: new Mukah Airport, Universiti Teknologi MARA (UiTM) campus, and Mukah Science Park. Mukah Coal Fired power plant started operation in April 2009. This was followed by Press Metal Sarawak opening its first aluminium smelting plant in August 2009.[29] In April 2011, Mukah new administrative centre was built that houses the head office of RECODA[29] and Dalat & Mukah District Council.[37] Since 2014, Matadeng Industrial park, located at 30 km from the Mukah town, was planned.[38][39] New Mukah Airport started construction in 2017 and commenced operation in June 2021.[40] Construction of new UiTM Mukah Campus started in 2012 and completed in 2015, capable of housing 2,000 students.[41] Three faculties are based in this new campus, namely: faculty of business management, faculty of plantation and agrotechnology, and faculty of Applied Science.[42] Mukah Rinwood 10 MW biomass power plant also started construction in 2015. It uses oil palm waste such as empty fruit branch, palm kernel shell, and mesocarp fibre to generate electricity.[33]

Balingian coal fired power plant began construction in 2015.[33] The power plant started operating in May 2019.[43][44]

Tanjung Manis

Tanjung Manis aims to become a palm oil integrated centre and halal food hub.[36] Tanjung Manis Halal Hub was launched in February 2009.[29] Other projects planned includes building an integrated port and deep sea fishing port. In 2013, Sea Party International Co Ltd from Taiwan invested in this area, involving in tilapia, marine fish, and shrimp farming projects.[29]

Baram

The Baram region encompasses Miri, Marudi, Telang Usan, and Beluru. It aims develop highland agriculture, livestock rearing, and ecotourism.[45] Construction of IHAS started in 2015.[46] Access roads to Baram Dam and Murum Dam were also planned.[29]

Tunoh

Similar to Baram, Tunoh also aims to become an agriculture and eco-tourism centre. Access road to Baleh Dam was planned in 2013.[29] Access road to Tunoh and a new township at Bukit Mabong was planned in 2016.[47]

Results

As of 2014, 19 projects with more than RM 32 billion in FDI has been approved cumulatively. Of these projects, 15 of them were located in Samalaju, and the remaining four were located in Tanjung Manis, Mukah and Kidurong.[31] In the year 2014 alone, SCORE accounted for 90% of Sarawak's total foreign direct investment (FDI), amounting RM 9.6 billion, where 87.2% the investments were foreign.[48] As of 2016, 16 projects in basic metal products industry, two projects in chemical industry, two projects under food manufacturing, and one project under petrochemical industry was approved.[17] As of 2018, a total of nine projects were operational in the economic corridor, where seven of them were located in Samalaju, one each at Mukah and Tanjung Manis. SCORE recorded RM 79.97 billion in total investments, where RM 33.64 billion (42%) came from private investments.[49] As of 2020, SCORE created 6,654[50] to 18,000 job opportunities.[51] A total of 68% of the jobs were filled by locals.[50] Export values worth RM 9.4 billion were generated in the same year.[50] As of October 2021, cumulative private and public investments in SCORE stood at RM 71.1 billion, where public sector contributes 58.2% and foreign investments stood at 36.7%.[52] In the year of 2022, total cumulative investments in SCORE stood at RM 102.36 billion where RM93.09 billion was contributed by the private sector and RM 9.17 billion contributed by public sector,[53] where figures from 2021 annual report was quoted.[14]

Sarawak failed to achieve a developed and industrialised state within Malaysia by the year 2020.[54] RECODA stopped publishing annual reports after merging with "Post Covid-19 development strategy" in 2021.[55] As of 2023, 84 out of 251 of the projects implemented by RECODA were completed.[56]

Breakdown of recorded investments in RECODA annual reports
Year Public Investments
(in RM billion)
Private Investments
(in RM billion)
Jobs No
2012[18] Mukah (cumulative) 4.0 Samalaju (cumulative) 29.0 Samalaju (cumulative) 17,333
Murum dam 3.0 Sea Party (Tanjung Manis) 1.9
Samalaju water supply 0.1 Mukah Press Metal 1.0
Samalaju Port 1.8
2013[29] 9th Malaysian Plan (2008-2010) 6.58 Sea Party (Tanjung Manis) 2.0 TERAJU 3,459
10th Malaysian Plan (2011-2013) 4.0
2014[57] 9th Malaysian Plan (2008-2010) 6.6
10th Malaysian Plan (2011-2014) 3.8
2015[33] 9th Malaysian Plan (2008-2010) 6.6 Total >30 Samalaju 6,500
10th Malaysian Plan (2011-2015) 3.8 Construction 10,000
2016[47] Samalaju 1.4 Samalaju Growth Node 35.2 Samalaju 31,160
Mukah 1.0 Mukah 1.8 Mukah 3,408
Tanjung Manis 2.2 Tanjung Manis 2.2 Tanjung Manis 1,212
Tunoh 0.43 Tunoh 0.002 Tunoh 4,229
Baram 0.24 Baram 3.0 Baram 412
Power generation and transmission excluding Bakun Dam 0.0 Power generation and transmission excluding Bakun Dam 17.1 Power generation and transmission excluding Bakun Dam 12,200
Pan Borneo Highway (within SCORE area) 6.03 Pan Borneo Highway (within SCORE area) 0.0 Pan Borneo Highway (within SCORE area) 3,575
2017[22] Mukah (2009-2017) 0.45 Samalaju steel project 12.7 Samalaju 6,300
Samalaju (2009-2017) 1.34 Samalaju methanol project 8.5
Tanjung Manis (2009-2017) 0.5
Tunoh (2009-2017) 1.54
Baram (2009-2017) 0.26
Access road to Murum HEP (2009-2017) 0.69
Sangan - Sg Anap Road (2009-2017) 0.23
2018[28] 11th Malaysian Plan (2016-2020) 3.9 Total 39.94 Total 17,828
State projects 4.5
2019[58] URDA 1.5 Samalaju 29.0 Samalaju 14,414
HDA 1.5 Mukah 1.0 Mukah 900
NRDA 1.5 Tanjung Manis 2.3 Tanjung Manis 1,852
Tanjung Kidurong 8.2 Tanjung Kidurong 725
2020[59] URDA 1.5 Samalaju 42.0 Samalaju 23,424
HDA 1.5 Mukah 1.0 Mukah 900
NRDA 1.5 Tanjung Manis 2.3 Tanjung Manis 2,480
Tanjung Kidurong 2.3 Tanjung Kidurong 1,888
2021[14] 9th Malaysian Plan (2008-2010) 0.98 Samalaju (cumulative) 31.24 Samalaju 12,770
10th Malaysian Plan (2011-2015) 1.6
11th Malaysian Plan (2016-2020) 1.8
12th Malaysian Plan (2021-2025) 0.12
NRDA 1.5
HDA 1.5
URDA 1.5
Talent and Community Development 0.024
Total recorded investments in RECODA annual reports
Year Public
(in RM billion)
Private
(in RM billion)
Total
(in RM billion)
No. of Jobs
2012 9.2 31.9 41.1 17,333
2013 10.58 2.0 12.58 3,459
2014 10.38
2015 10.38 30.0 40.38 16,500
2016 11.3 59.4 70.76 56,196
2017 5.02 21.2 26.22 6,300
2018 46.4 33.6 80 17,093
2019 4.5 40.5 45 17,891
2020 4.5 60.45 64.95 27,851
2021 9.17 93.09 102.3 12,770

Analysis

According to a report published in 2011, although SCORE helps to diversify Sarawak energy sources away from fossil fuels, it met several technical challenges such as a lack of proper highways to carry raw materials into rural areas, lack of proper electricity networks to carry power to consumers, difficulties in river diversion, tunneling, channeling, transportation of machines and turbines to the dam construction sites, and lack of highly trained engineers and construction workers to build the spillways, powerhouses, transformers, turbines, and dam face. The turbid river waters are filled with silt, sediments, logs, and rocks due to logging, erosions, and unsustainable agricultural practices. Such low quality river waters can make dam projects more complicated and shorten the lifetime of the dam usage to 30 to 40 years. These problems could make the electricity generated from SCORE unaffordable because of cost overruns and delays in financing the projects. An example is the cost overruns of Bakun Dam six times higher than the original price of RM 2.5 billion due to delays, rising interest rates, strikes and problems with excavations. Initially, construction companies have to underestimate their risks in order to have an edge in the tender bidding process. When problems emerged during constructions, additional payment have to be made in order to keep the project afloat, thus making the electricity generated by dams in Sarawak to be two to three times higher than expected.[5] Building dams in the middle of the forests can be construed as high risk project as it deals with many problems such as logistical issues, indigenous communities and their lands, contractors and corruptions. The caused the investors to be risk averse, thus leading to delay in financing. The electrical energy generated from the dams are mainly for industry players, instead for local population. One respondent from the interview predicted that "the amount of jobs created for the local population is practically zero". Besides, the policy of SCORE to attract "energy inefficient" metal smelters is a waste of electricity. The construction of dams also causes environmental damage due to logging, changes in water biochemical profile, emission of methane gas from rotten vegetation, and submersion of tropical rainforests.[5]

A study done in March 2015 at University of California showed that distributed energy plants such as solar and biomass can meet the future energy demand of the state when compared to dam construction.[60] A study conducted by Universiti Malaysia Sabah concluded that there is a potential for agricultural development in SCORE because of the Sarawak government and Development Bank of Sarawak (DBOS) commitments to developing this industry. However, encouraging youths to participate in this industry would be a major challenge.[61]

See also

References

  1. ^ "5 major national corridors to translate county's development agenda: Zahid [NSTTV]". New Straits Times. 22 April 2018. Archived from the original on 22 April 2018. Retrieved 4 December 2021.
  2. ^ a b c d "Sarawak Corridor of Renewable Energy (SCORE)". Sarawak Manufacturers Association. Archived from the original on 25 November 2021. Retrieved 4 December 2021.
  3. ^ a b "Laws of Sarawak Chapter 64 - Regional Corridors Development Authority Ordinance 2006" (PDF). Sarawak state government. Archived from the original (PDF) on 1 August 2019. Retrieved 5 December 2021.
  4. ^ "Majlis Pelancaran Koridor Sarawak - Sarawak Corridor of Renewable Energy (SCORE)". Koleksi Arkib Ucapan Ketua Eksekutif. 11 February 2008. Retrieved 31 July 2019.
  5. ^ a b c d e f K. Sovacool, Benjamin; Bulan, L.C. (2011). "Meeting Targets' Missing People: The Energy Security Implications of the Sarawak Corridor of Renewable Energy (SCORE)". Contemporary Southeast Asia. 33 (1): 56. doi:10.1355/cs33-1c. ISSN 0129-797X.
  6. ^ Jack, Wong (22 July 2014). "Bakun at 50% capacity producing 900MW". The Star (Malaysia). Retrieved 23 November 2015.
  7. ^ Christopher, Lindom (11 July 2015). "Making HEPs in Sarawak safe". New Sarawak Tribune. Archived from the original on 23 November 2015. Retrieved 23 November 2015. ... Murum HEP had officially started commercial operation on 8 June 2015,"...
  8. ^ Ogilvy Ruekeith, Geryl (19 November 2015). "Baram dam project halted indefinitely". The Borneo Post. Archived from the original on 12 June 2021. Retrieved 7 May 2022.
  9. ^ Povera, Adib (16 August 2017). "Sarawak Energy completes acquisition of Bakun Dam". New Straits Times. Archived from the original on 31 August 2020. Retrieved 7 May 2022.
  10. ^ Wong, Jack (30 November 2020). "Baleh main dam to be built soon". The Star (Malaysia). Archived from the original on 18 April 2021. Retrieved 7 May 2022.
  11. ^ Siew Yean, Tham. "2022/45 "Hydropower Development in Sarawak: Sensitivities over Sustainability and China's Involvement"". ISEAS Yusof Ishak Institute, Singapore. Archived from the original on 28 April 2022. Retrieved 7 May 2022.
  12. ^ "FMM Sarawak - State News". Federation of Malaysian Manufacturers. Archived from the original on 4 March 2021. Retrieved 13 January 2022.
  13. ^ Kah Yen, Ow (2015). Determinants of foreign direct investment in the manufacturing sector of Sarawak (Bachelor of Economics thesis). Universiti Malaysia Sarawak.
  14. ^ a b c "RECODA 2021 annual report" (PDF). RECODA. Archived from the original (PDF) on 19 July 2023. Retrieved 19 July 2023.
  15. ^ "1.5 million jobs by 2030". The Star (Malaysia). 7 August 2008. Archived from the original on 6 January 2022. Retrieved 6 January 2022.
  16. ^ "Sarawak sets "Sarawak Gemilang 2030" vision". Astro Awani. 16 September 2013. Archived from the original on 6 January 2022. Retrieved 6 January 2022.
  17. ^ a b c d "Sarawak Corridor of Renewable Energy - Powering the Future" (PDF). State Planning Unit - Chief Minister Department. Archived from the original (PDF) on 18 July 2017. Retrieved 6 January 2022.
  18. ^ a b c "Annual Report 2012 - Regional Corridor Development Authority" (PDF). Regional Corridor Development Authority (RECODA). Archived from the original (PDF) on 7 August 2023. Retrieved 7 August 2023.
  19. ^ a b c d e Veno, Jeremy. "Three agencies under Recoda established, Score expected to generate RM334 bln". The Borneo Post. Archived from the original on 30 May 2021. Retrieved 12 December 2021.
  20. ^ a b c "Five sub-committees to prepare list of NRDA projects". The Borneo Post. 29 July 2018. Archived from the original on 6 June 2021. Retrieved 12 December 2021.
  21. ^ a b c "Regional Development Agencies". RECODA. Archived from the original on 12 December 2021. Retrieved 12 December 2021.
  22. ^ a b c "RECODA annual report 2017" (PDF). RECODA. Archived from the original (PDF) on 12 February 2022. Retrieved 12 February 2022.
  23. ^ a b c d "ReadCoda Newsletter 2020" (PDF). RECODA. Archived from the original (PDF) on 23 December 2021. Retrieved 23 December 2021.
  24. ^ Johari, Zaheera (2 November 2018). "Development in HDA areas to benefit about 75,000 inhabitants". The Borneo Post. Archived from the original on 2 June 2021. Retrieved 17 December 2021.
  25. ^ "SCORE's new agency HDA starts on a ahigh note". New Sarawak Tribune. 20 July 2017. Archived from the original on 31 July 2019. Retrieved 19 December 2021.
  26. ^ "New SCORE agency to accelerate development in highland areas". The Borneo Post. 19 July 2017. Archived from the original on 10 June 2021. Retrieved 23 December 2021.
  27. ^ Chua, Sam (5 September 2022). "Integrated highland agro-station in Long Banga now under Manred management". The Borneo Post. Archived from the original on 5 September 2022. Retrieved 19 July 2023.
  28. ^ a b "RECODA 10th anniversary 2018 annual report" (PDF). RECODA. Archived from the original (PDF) on 18 February 2022. Retrieved 18 February 2022.
  29. ^ a b c d e f g h i Regional Corridor Development Authority Annual Report 2013 (PDF). RECODA. 2013. p. 50. Archived from the original (PDF) on 10 May 2021.
  30. ^ "Samalaju Industrial Park (SIP): The engine room of SCORE". RECODA. Archived from the original on 30 May 2017. Retrieved 30 November 2021.
  31. ^ a b c "Sarawak scores high on foreign investments". The Borneo Post. Archived from the original on 12 June 2021. Retrieved 12 November 2015.
  32. ^ Wong, Jack (13 August 2018). "Sarawak corridor attracts RM79.3bil in investments". The Star (Malaysia). Archived from the original on 29 September 2020.
  33. ^ a b c d "2015 Annual Report - Regional Corridor Development Authority" (PDF). RECODA. Archived from the original (PDF) on 10 February 2022. Retrieved 10 February 2022.
  34. ^ "DCM: Statistics needed to review investment impact on Samalaju Industrial Park". The Borneo Post. Archived from the original on 3 June 2021. Retrieved 4 December 2021.
  35. ^ "Annual Report 2019 - Regional Corridor Development Authority" (PDF). Regional Corridor Development Authority (RECODA). Archived from the original (PDF) on 23 December 2023. Retrieved 21 December 2023.
  36. ^ a b Sibon, Peter (9 July 2014). "Baram, Tunoh/Baleh identified as two growth nodes within SCORE under 11MP". The Borneo Post. Archived from the original on 31 May 2021. Retrieved 31 December 2021.
  37. ^ "Service Provider Profiles". Service Sarawak. Archived from the original on 27 January 2022. Retrieved 27 January 2022.
  38. ^ Sibon, Peter (25 March 2014). "Drawing up plan for integrated industrial area at Matadeng". The Borneo Post. Archived from the original on 5 June 2021. Retrieved 14 January 2022.
  39. ^ "Investment Booklet" (PDF). RECODA. Archived from the original (PDF) on 14 January 2022. Retrieved 14 January 2022.
  40. ^ "New Mukah Airport to start operating on Thursday (June 17), says Dr Wee". The Star (Malaysia). Archived from the original on 24 June 2021. Retrieved 14 January 2022.
  41. ^ "UiTM Mukah". Hock Seng Lee Construction. Archived from the original on 14 May 2021. Retrieved 14 January 2022.
  42. ^ "UiTM Cawangan Sarawak Mukah Campus". UiTM Sarawak. Archived from the original on 17 April 2021. Retrieved 14 January 2022.
  43. ^ 王, 桀 (14 May 2019). "马来西亚巴林基安循环流化床燃煤机组项目1号机组投运 (Malaysian Balingian circulating fluidisized bed coal-powered generator unit 1 commenced operation)". 北极星电力网 (Bei Ji Xin Energy Grid). Archived from the original on 1 September 2019. Retrieved 24 January 2020.
  44. ^ 蒋, 武林 (5 July 2019). "中国能建湖南火电承建马来西亚巴林基安项目2号机组商运 (China Energy Engineering Group Hunan Power Conctruction Co Ltd undertakes Malaysian Balingian generator unit 2 for commercial operation)". 北极星电力网 (Bei Ji Xin Energy Grid). Archived from the original on 1 September 2019. Retrieved 24 January 2020.
  45. ^ "Baram Growth Area". RECODA. Archived from the original on 2 January 2022. Retrieved 2 January 2022.
  46. ^ "Muhyiddin to adopt two villages in Baram". Malaysiakini. 14 May 2015. Archived from the original on 9 June 2021. Retrieved 2 January 2022.
  47. ^ a b Regional Corridor Development Authority 2016 Annual Report (PDF). Sarawak: RECODA. 2016. pp. 1–104. Archived from the original (PDF) on 27 May 2019. Retrieved 4 January 2022.
  48. ^ Alias, Nor Zahidi. "Economic Research - State of Sarawak". Malaysian Rating Corporation Berhad. Archived from the original on 18 November 2015. Retrieved 5 December 2021.
  49. ^ Teo, Ronnie (13 January 2019). "SCORE-ing greater success". The Borneo Post. Archived from the original on 14 June 2021. Retrieved 4 December 2021.
  50. ^ a b c "Sarawak secures RM15.7 bln in investments amid pandemic". The Borneo Post. Archived from the original on 7 November 2021. Retrieved 13 January 2022.
  51. ^ "SCORE has Generated Investments of RM39.94 billion and Created 18,000 Job Opportunities". RECODA. Archived from the original on 7 January 2022. Retrieved 7 January 2022.
  52. ^ Tuah, Yvonne (15 January 2022). "A look at Sarawak's SCORE card". The Borneo Post. Archived from the original on 15 January 2022. Retrieved 20 May 2022.
  53. ^ "Sarawak scores record investments worth RM102.36 bil in 2022, says Hanifah". The Edge (Malaysia). 23 February 2023. Archived from the original on 20 March 2023. Retrieved 9 April 2023.
  54. ^ Jianing, Xu (2020). Ahn, Y.; Wu, F. (eds.). "The Economic Impact of Malaysia's Institution on the Failure of the Wawasan 2020". E3S Web of Conferences. 214: 02005. doi:10.1051/e3sconf/202021402005. ISSN 2267-1242.
  55. ^ "Annual Report". Archived from the original on 3 January 2024. Retrieved 3 January 2024.
  56. ^ "Recoda CEO: 84 of 251 projects implemented in 2023 completed". The Borneo Post. 1 January 2024. Archived from the original on 15 January 2024. Retrieved 26 March 2024.
  57. ^ "Annual Report 2014 - Regional Corridor Development Authority" (PDF). Regional Corridor Development Authority (RECODA). Archived from the original (PDF) on 3 January 2024. Retrieved 7 August 2023.
  58. ^ "Annual Report 2019 - Regional Corridor Development Authority" (PDF). Regional Corridor Development Authority (RECODA). Archived from the original (PDF) on 3 January 2024. Retrieved 3 January 2024.
  59. ^ "Annual Report 2020 - Regional Corridor Development Authority" (PDF). Regional Corridor Development Authority (RECODA). Archived from the original (PDF) on 3 January 2024. Retrieved 3 January 2024.
  60. ^ Shirley, Rebekah; Kammen, Daniel (July 2015). "Energy planning and development in Malaysian Borneo: Assessing the benefits of distributed technologies versus large scale energy mega-projects". Energy Strategy Reviews. 8: 15–29. doi:10.1016/j.esr.2015.07.001.
  61. ^ Salleh, Norhuda; Mansur, Kasim (25 May 2020). Pembangunan Sumber di Luar Bandar (Resource development in rural areas). Universiti Malaysia Sabah. pp. 34–35. ISBN 9789672962199. Retrieved 2 April 2023.


Kembali kehalaman sebelumnya