The Victorian Desalination Plant[2] (also referred to as the Victorian Desalination Project or Wonthaggi desalination plant) is a water desalination plant in Dalyston, on the Bass Coast in southern Victoria, Australia. The project was announced by Premier Steve Bracks in June 2007,[3] at the height of the millennium drought when Melbourne's water storage levels dropped to 28.4%, a drop of more than 20% from the previous year. Increased winter-spring rains after mid-2007 took water storage levels above 40%,[4] but it was not until 2011 that storages returned to pre-2006 levels.
The plant was completed in December 2012, and was the largest addition to Melbourne's water system since the Thomson River Dam was completed in 1983. However, at the time, Melbourne's reservoirs were at 81% capacity, and the plant was immediately put into standby mode.[5] The first water released for public use was in March 2017 via Cardinia Reservoir.
As a rainfall-independent source of water the desalination plant complements Victoria's existing drainage basins, being a useful resource in times of drought. It is a controversial part of Victoria's water system, with ongoing costs of $608 million a year,[6] equivalent to .16% of Melbourne's FY2019 GDP,[7] even if no water is ordered. Construction commenced in mid-2009.[8] While the project will supply water for Melbourne, it is being managed by the Department of Sustainability & Environment (DSE) as a public-private partnership (PPP). DSE awarded the tender for design, build and operation to another company that will in turn supply the water to Melbourne Water, that makes payments to the plant owners and operators, Aquasure (Ventia/Suez). Melbourne Water pays the owner of the plant, even if no water is ordered, $608 million a year.[6] That is $1.8 million per day, for 27 years.[5] The total payment is expected to be between $18 and $19 billion.[5] On 1 April each year, the Minister for Water places an order for the following financial year, up to 150 gigalitres a year, at an additional cost to Melbourne Water and consumers.[5]
Proposal
The potential for a desalination plant was promoted through the late 2000s in response to an increasingly severe drought which saw Melbourne's water storages go from 57.1% of capacity in January 2005 to 28.7% in June 2007.
The project was part of the Victorian Government's"Our Water, Our Future" water plan which included associated projects such as the North-South Pipeline, the Cardinia Pipeline and a proposed interconnector to Geelong.[9]
The total average inflow into Melbourne dams from 1913 to 1996 was 615 gigalitres (2.17×1010 cu ft) per year, while average inflow 1997–2009, during Victoria's most severe recorded drought was 376 gigalitres (1.33×1010 cu ft) per year.[10][1]
The combination of drought and rapid population growth put pressure on reserve storage capacity which had dropped from 97.8 per cent in 1983 to just over one-quarter of maximum capacity in 2007.[11][12] As a result, water restrictions were in place for several years.[13]
The desalination plant and associated infrastructure includes tunnels connecting the plant to marine intake and discharge structures up to 1.2 km (1⁄2 mi) out to sea, an 85-kilometre (55 mi) pipeline to connect the plant to Melbourne's water supply system, and power supply infrastructure for the plant.
The plant can provide up to 150 gigalitres (5.3×109 cu ft) of additional water a year, with the potential to expand production to 200 gigalitres (7.1×109 cu ft) per year.[14]
A two-headed marine structure extends up to 2 km (1 mi) offshore was to be temporarily constructed. The plant takes in 480 billion litres (1.1×1011 imp gal; 1.3×1011 US gal) of seawater and pumps back 280 billion litres (6.2×1010 imp gal; 7.4×1010 US gal) of saline concentration every year.[15]
A six turbine windfarm was built in 2005 and is located at Glenthompson to offset the facility's electricity use.[16]
Estimated water production is 150 gigalitres (5.3×109 cu ft) of desalinated water per year, potentially providing around a third of Melbourne's annual water consumption (based on 2007 consumption levels). It is intended that the water produced will be supplied to Melbourne, Geelong, Western Port and South Gippsland.
The intake pipes for the desalination plant are located over 1 kilometre (1⁄2 mi) out to sea.[17]
Environmental effects studies
In August 2008, a 1,600-page environmental effects study report was prepared and found that; "...several protected species could be affected by the plant's construction and operation – including the orange-bellied parrot, the growling grass frog and the giant Gippsland earthworm – but none would be left "significantly" worse off.". The community was given 30 business days to respond to the report.[15] Watershed Victoria claimed that this was insufficient time for community groups to analyse the report and prepare submissions.
On 30 June 2009, the AquaSure consortium, which is made up of Degrémont, Macquarie Capital and Ventia Contractors, was named the winning bidder.[16] Simultaneously, it was announced that construction was scheduled to commence in late 2009, proposing that water be delivered by late 2011.[20]
A$1.8 million per day fee is payable to the construction consortium. This minimum fee that is payable for 27 years after completion. Even if no water is required, the total payment is between $18 and $19 billion.[5]
Location
Nine sites were included in the feasibility study's "long list", and subsequently reduce to four (Surf Coast, East of Port Philip Bay, West of Western Port, and Bass Coast). The Bass Coast was chosen as the premium location.[14] Compulsory acquisition notices were issued to affected residents on 25 January 2008.[21]
The site is a 20-hectare (49-acre) area in Dalyston next to Williamsons Beach on the Bass Coast in south-eastern Victoria. It is between Wonthaggi and Kilcunda and near the Powlett River.
The site is located on Bunurongaboriginal land, specifically the Boakoolawal clan which lived in the area south of the Bass River before white settlement. Middens containing charcoal and shellfish mark the location of their campsites along the coast.[22] Many significant archaeological artifacts have previously been discovered around the construction site,[23] including Australia's first dinosaur bone, the Cape Paterson Claw, discovered nearby in 1903 by William Ferguson near what is now Eagles Nest, Bunurong Marine National Park in Inverloch.[24]
Plans are underway to build a much larger, wind farm at Glenthompson to offset the electricity used by the desalination plant.[16]
The site is located in the Powlett River Coal Fields where the State Coal Mine produced most of the steam-locomotive fuel that serviced the Victorian Railways network, from 1911 until 1978.[25]
Cost
The capital cost for the project was initially estimated to be $2.9 billion in the initial feasibility study; this was later revised to $3.1 billion[26] and then to $3.5 billion. After the winning bidder was announced it was revised to $4 billion.
Operating costs are to be charged by a private firm over a 25–30-year period and are estimated to be around $1.5 billion. This cost includes labour, replacement of membranes, chemicals costs and energy, and it was initially estimated at $132 million per annum.[27] Unlike previous water infrastructure works in Melbourne, the plant will be built and operated as a public-private partnership.
A 2008 report by the Water Services Association of Australia, modelling several national water-supply scenarios for 2030. It determined that sourcing water supply by seawater desalination was the most energy-intensive. The report predicted that if desalination was the primary source of supplying around 300 litres (66 imp gal; 79 US gal) per person per day, energy use would rise by 400% above today's levels.[28]
On 12 December 2009 The Age newspaper published details of considerable areas of land made cheaply available to the plant's developers without the value of that land being included in the project's official costs.[29]
The average water bill for residents living in Melbourne was estimated to rise by more than 60 per cent over the following five years, while the Essential Services Commission estimated it might rise up to 96 per cent.
Then Water Minister Tim Holding, stated that; "Melbourne residents need to help pay for major water infrastructure projects, such as the desalination plant and the Sugarloaf (North South) pipeline."[30]
By comparison, the Kwinana Desalination Plant in Perth, Western Australia, was completed in 2006 with approximately 30–50 per cent of the output of the Wonthaggi plant. It cost $387 million to build and did not include an 85 km (55 mi) pipeline and windfarm.
Energy consumption
The plant is estimated to require 90 MW of electricity to power the plant and transfer pipeline when operating at 150GL capacity.
The owners state it is 100% offset by renewable energy, however they also state it would be "impractical" to directly supply the plant with renewable energy sources such and wind and solar, instead purchasing "renewable energy credits" (also known as Carbon Credits) to offset the coal powered energy the plant in fact uses.[31]
Opposition
The project encountered opposition from community groups and local residents, and the Australian Greens and the business fundamentals were challenged during feasibility studies and assessments of Melbourne's water supply needs.[32]
Regular public rallies were conducted on the site and in Melbourne.
The community group Your Water, Your Say was one of the first organised opposition group. It was sent bankrupt after it lost a legal case after the group pursued the Victorian Government over lack of reports and consultation. The case centred on initial water requirement figures, feasibility studies and environmental effects reports among other issues. More recently, a new opposition group Watershed Victoria, has continued the opposition campaign.
The government pursued legal costs, which sent the group bankrupt.[33]
At a July 2008 protest several people were removed from Crown land, but none were arrested.[35]
In June 2009, a petition including 3,000 signatories opposing the plant was presented to the Victorian Parliament.[36]
Your Water Your Say v Minister for the Environment, Heritage and the Arts
Your Water Your Say (YWYS) opposed the proposal, taking legal action against the Victorian State Government regarding non-disclosure of financial information and lack of environmental studies and reports.[37] As of July 2008 YWYS lost the action, and the Federal Court awarded costs to the State Government estimated to be up to $200,000, effectively rendering the community group broke.[33] YWYS was subsequently disbanded.
In its submission response to the Environmental Effects Statement, YWYS stated: "The Federal and State Governments are aware that YWYS is unlikely to be in a position to pay its significant legal costs and hence their apparent inability to make a decision on this front can only be interpreted as an attempt to further avoid community scrutiny of this project."[38]
Sharing of private information with private consortia
In December 2009, it was revealed that private information obtained by Victoria Police during surveillance efforts on individuals involved or corresponding with YWYS, Watershed Victoria and other community groups, had been made available to the private consortium building the desalination plant, Aquasure, via a memorandum between the State Government, Victoria Police and Aquasure.[39] Victoria Police responded by explaining that the information would be used to better "manage" future activities and potential "security threats".[39]
Public access
Booked tours are run and plans are underway for Aquasure to open to the public. The gates open daily for public access to the 225-hectare (560-acre) park and 8 kilometres (5 mi) of walking, horse riding and cycling tracks. The plant is located next to Williamsons Beach and the Wonthaggi Wind Farm, Wonthaggi.[40]
Timeline
2007
19 June – the Victorian Government announced its intention to develop a seawater reverse osmosis desalination plant on the coast near Wonthaggi. The plant is explained to be part of a water plan marketed as Our Water Our Future.[41]
28 December – the Minister for Planning for the Victorian Government determines that the project would require assessment under the Environment Effects Act 1978 and preparations for an Environment Effects Statement (EES) begin.
2008
25 January – Compulsory acquisition notices issued to the residents of the proposed site.
4 February – the Federal Government determines that the project will have to require approval under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).
21 February – 13 March – draft scoping requirements for the EES placed on public exhibition.
4 May – final scoping requirements for the EES issued.
13 June – Justice Heerey awards costs to the Federal and State Governments a result of the action – Your Water Your Say v Minister for the Environment, Heritage and the Arts & Anor; Federal Court Proceeding VID188/2008.
5 July – The plant is addressed during the Climate Emergency Rally at various locations in Melbourne.
100 m (330 ft) of coastline is landscaped to alter the flow of Powlett River.
20 August – 30 September – Environment Effects Statement (EES) released for public comment by the State Government, community given 5 weeks to submit responses to the 1,600-page report.
2009
11 January – Planning Minister, Justin Madden, approved a planning scheme amendment to allow for a pilot desalination plant to come into effect on 17 January.[42]
30 July – Winning bidder for construction announced.
6 October – Construction commenced.
2010
4 February – First sections of the new pipeline are laid
2012
Production and related operations commenced at end of year
"Zero water order" for financial year 2012–2013 and plant immediately put into standby mode[5]
Owing to dry conditions, two consecutive orders were placed for 100 GL and 125 GL of water, expected to meet a quarter of Melbourne's water demand, placing upwards pressure on water prices.[43]
2035–2045
Contract for the operation of the plant expected to expire.
Media
Construction of the plant was described in an episode of Build It Bigger, which aired on the Discovery Channel and the Science Channel in the United States in 2011.[44]
Photos
Construction of pipeline to Melbourne from Wonthaggi desalination plant
Construction of pipeline to Melbourne from Wonthaggi desalination plant
Wonthaggi desalination plant construction in progress
Powlett River and rig near Wonthaggi desalination plant
Powlett River estuary near site of Wonthaggi desalination plant
Pangburn Ciudad PangburnUbicación en el condado de White en Arkansas Ubicación de Arkansas en EE. UU.Coordenadas 35°25′33″N 91°50′23″O / 35.425833333333, -91.839722222222Entidad Ciudad • País Estados Unidos • Estado Arkansas • Condado WhiteSuperficie • Total 1.63 km² • Tierra 1.63 km² • Agua (0%) 0 km²Altitud • Media 106 m s. n. m.Población (2010) • Total 601...
NaskahPapirus 121NamaP. Oxy. 4805Tanda P {\displaystyle {\mathfrak {P}}} 121TeksInjil Yohanes 19:17-18,25-26Waktuabad ke-3Aksarabahasa YunaniDitemukanOxyrhynchus, MesirKini diSackler LibraryKutipanR. Hatzilambrou, P. J. Parsons, J. Chapa, OP LXXI (London: 2007), pp. 9-11.Ukuran[4.5] x [3.3] cm (28 x 12)Jenistidak diketahuiKategoritidak adaCatatannomina sacra, diaeresis Papirus 121 (bahasa Inggris: Papyrus 121; dalam penomoran Gregory-Aland diberi kode siglum P {\displaystyle {\mathfr...
2003 single by Ayumi HamasakiForgivenessSingle by Ayumi Hamasakifrom the album Memorial Address ReleasedAugust 20, 2003GenreJ-popexperimentalelectronicLength22:29LabelAvex TraxSongwriter(s)Ayumi Hamasaki (lyrics)CREA + DAI (music)Producer(s)Max MatsuuraAyumi Hamasaki singles chronology & (2003) Forgiveness (2003) No Way to Say (2003) Official Music VideoForgiveness on YouTube Forgiveness is the 30th single released by Ayumi Hamasaki, and her 17th number one. It came out on August 20, 2003...
Pour les articles homonymes, voir Nodule. Cet article est une ébauche concernant la médecine. Vous pouvez partager vos connaissances en l’améliorant (comment ?) selon les recommandations des projets correspondants. Nodules En médecine, un nodule[1] est une formation anormale, arrondie, palpable dans ou sous la peau, qui peut être une tumeur bénigne ou maligne. Description Certains nodules peuvent être des tumeurs cancéreuses, en particulier dans le cancer du sein[2]. En règle ...
Cet article est une ébauche concernant une fête et la Finlande. Vous pouvez partager vos connaissances en l’améliorant (comment ?) selon les recommandations des projets correspondants. Drapeau finlandais dressé à Helsinki. Les fêtes et jours fériés en Finlande sont établis par l'Eduskunta, le parlement du pays. Selon la loi, le pavillon finlandais doit être déployé sur les bâtiments publics certains jours comme le 28 février (jour de Kalevala également connu sous l'appel...
The Theater Centeran image of orbachAddress210 West 50th StreetNew York CityUnited StatesOwnerCatherine RussellTypeOff-BroadwayCapacityJerry Orbach: 199Anne L. Bernstein: 199ProductionThe Fantasticks, Perfect CrimeOpenedMay 22, 2006Websitewww.thetheatercenter.com The Theater Center (known as The Snapple Theater Center until 2016) is a multi-theater entertainment complex located on the corner of 50th Street and Broadway in New York City. History The complex was built by actress and producer Ca...
50 First DatesPoster filmSutradara Peter Segal ProduserJack GiarraputoSteve GolinNancy JuvonenDitulis oleh George Wing PemeranAdam SandlerDrew BarrymoreRob SchneiderSean AstinLusia StrusBlake ClarkDan AykroydPenata musikTeddy CastellucciSinematograferJack N. GreenPenyuntingJeff GoursonPerusahaanproduksiHappy MadisonFlower FilmsDistributorColumbia PicturesTanggal rilis13 Februari 2004 (2004-02-13)Durasi99 menitNegara Amerika Serikat Bahasa Inggris AnggaranUS $75 jutaPendapatankotorU...
DailamiWakil Bupati Bener Meriah ke-4Masa jabatan12 Maret 2021 – 14 Juli 2022PresidenJoko WidodoGubernurNova IriansyahBupatiSarkawiPendahuluSarkawi Informasi pribadiLahir5 Februari 1974 (umur 49)Kenawat, Laut Tawar, Aceh Tengah, AcehKebangsaanIndonesiaPartai politik Partai Aceh Golkar GerindraSuami/istriSuryatiKarier militerPihak Gerakan Aceh MerdekaPertempuran/perangPemberontakan di AcehSunting kotak info • L • B Dailami, leb...
Occurrences and people in the Republic of Colombia throughout history This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: History of Colombia – news · newspapers · books · scholar · JSTOR (February 2018) (Learn how and when to remove this template message) The history of Colombia includes the settlements and soc...
Ice hockey team This article does not cite any sources. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: Hamilton Canucks – news · newspapers · books · scholar · JSTOR (December 2009) (Learn how and when to remove this template message) Hamilton CanucksCityHamilton, OntarioLeagueAmerican Hockey LeagueOperated1992–1994Home arenaCopps ColiseumAffiliateVancouver Canu...
Halaman ini berisi artikel tentang manga Jepang. Untuk festival Jepang, lihat Hinamatsuri. HinamatsuriSampul manga volume pertamaヒナまつりGenreKomedi[1]Penggalan kehidupan[2]Yakuza[1] MangaPengarangMasao ŌtakePenerbitEnterbrainPenerbit bahasa InggrisNA One Peace BooksMajalahHartaDemografiSeinenTerbit15 Juni 2010 – 15 Juli 2020Volume19 Seri animeSutradaraKei OikawaProduserMitsuhiro OgataNoritomo IsogaiShintarō YoshitakeKazufumi KikushimaHiroyasu TaniguchiToyok...
David Healy Informasi pribadiNama lengkap David Jonathan HealyTanggal lahir 5 Agustus 1979 (umur 44)Tempat lahir Killyleagh, Irlandia UtaraTinggi 1,73 m (5 ft 8 in)Posisi bermain StrikerInformasi klubKlub saat ini SunderlandNomor 23Karier senior*Tahun Tim Tampil (Gol) 1999–200120002000–20012001–2004200320032004–20072007–20082008– Manchester United→ Port Vale (pinjam)→ Preston North End (pinjam)Preston North End→ Norwich City (pinjam)→ Norwich City (pinj...
British children's television series Not to be confused with Mr. T or Jibber Jabber (TV series). This article has multiple issues. Please help improve it or discuss these issues on the talk page. (Learn how and when to remove these template messages) This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: Jibba Jabba – news · newspap...
Li Jue李傕Setelah kematian Dong Zhuo, Guo Si dan Li Jue menjarah ibukota Han di Chang'an. Ini adalah ilustrasi Dinasti Qing yang menggambarkan penyerangan itu.Marsekal Agung (大司馬)Masa jabatan195 (195) – 198 (198)Penguasa monarkiKaisar Xian dari HanJenderal Kereta dan Kavaleri (車騎將軍)Masa jabatan192 (192) – 195 (195)Penguasa monarkiKaisar Xian dari HanPembantu Direktur Kolonel (司隸校尉)Masa jabatan192 (192) – 195...
Canadian TV audio service Not to be confused with MAXTRAX. Television channel Max TraxMax Trax logoCountryCanadaBroadcast areaNationalHeadquartersToronto, OntarioOwnershipOwnerStingray DigitalHistoryLaunchedSummer 1997ClosedOctober 1, 2009Former namesDigital Music Express (1997 - 1999)DMX (1999 - 2002) Max Trax was a Canadian pay television audio service that broadcast continuous streaming music on multiple channel feeds. The service was owned by Stingray Digital. Originally known as Digital ...
Software for solving satisfiability problems Z3 Theorem ProverOriginal author(s)Microsoft ResearchDeveloper(s)MicrosoftInitial release2012; 11 years ago (2012)Stable release4.12.2[1] / 12 May 2023; 6 months ago (12 May 2023) Repositorygithub.com/Z3Prover/z3 Written inC++Operating systemWindows, FreeBSD, Linux (Debian, Ubuntu), macOSPlatformIA-32, x86-64, WebAssembly, arm64TypeTheorem proverLicenseMIT LicenseWebsitegithub.com/Z3Prover Z3, also known...
Hackathon Merdeka, Merdeka dengan kode! Hackathon Merdeka adalah sebuah ajang kompetisi pembuatan aplikasi komputer (software) yang difasilitasi oleh Kantor Staf Presiden Republik Indonesia dan diselenggarakan oleh komunitas Code4Nation yang bertujuan mencari solusi terbaik bagi permasalahan bangsa.[1] Pembuatan aplikasi komputer yang diperlombakan adalah aplikasi pemantau harga komoditas, terutama tiga bahan pokok yang dianggap paling strategis, yaitu beras, gula, dan daging. Aplikas...
Pour un article plus général, voir commission de vérité et de réconciliation. Commission de la vérité et de la réconciliationHistoireFondation 1996Dissolution 21 mars 2003CadreSigle (en) TRCType Commission of inquiryPays Afrique du SudOrganisationFondateur Nelson MandelaPrésident Desmond TutuSite web www.justice.gov.za/trcmodifier - modifier le code - modifier Wikidata La Commission de la vérité et de la réconciliation (CVR) en Afrique du Sud a été créée par le Prom...