Ashington, previously known as Hirst, is a railway station on the Northumberland Line which is due to reopen in December 2024.[1] Trains will run between Newcastle and Ashington. The station will serve the town of Ashington in Northumberland, England.
The station's signal box was closed on 14 February 2010, with the removal of the main line crossover. The signal box was demolished over the weekend of 10–11 August 2013.[citation needed]
The northbound platform was partially demolished in October 2022 to make space for the new Northumberland Line platform.[2]
Reopening proposals
Proposals to reintroduce passenger rail services to the currently freight-only section of the former Blyth and Tyne Railway system have been discussed since the 1990s.[3][4][5]
In the early 2010s, Northumberland County Council (NCC) became interested in the proposals, commissioning Network Rail to complete a GRIP 1 study to examine the best options for the scheme in June 2013.[6] This report was published in March 2014 and was followed in June 2015 with the commissioning of a more detailed GRIP 2 study at a cost of £850,000.[7] The GRIP 2 study, published in October 2016, confirmed that the reintroduction of a frequent seven-day a week passenger service between Newcastle, Ashington and possibly a new terminus to the east, at Woodhorn, was feasible and could provide economic benefits of £70 million with more than 380,000 people using the line each year by 2034.[8] Despite a change in the political leadership of Northumberland County Council following the 2017 local elections[9] the authority continued to develop the project,[10] encouraged by the Department for Transport's November 2017 report, A Strategic Vision for Rail, which named the line as a possible candidate for a future reintroduction of passenger services.[11][12] Consequentially, NCC commissioned a further interim study in November 2017 (dubbed GRIP 2B) to determine whether high costs and long timescales identified in the GRIP 2 Study could be reduced by reducing the initial scope of the project, but the report failed to deliver on this.[13]
Nonetheless, the county council has continued to develop the project, hiring AECOM and SLC Rail as contractors to develop the scheme on their behalf in 2018[14] and allocating an additional £3.46 million in funding for a further business case and detailed design study[15] (equivalent to GRIP 3)[13] in February 2019.[15] Revised plans were revealed in July 2019 which were reduced in scope from the 2016 GRIP 2 study and proposed 4-phase project[16] to reduce the initial cost of the scheme. Phase 1 (at an estimated cost of £90 million)[15] would have seen hourly passenger trains[14] return to a reopened Ashington station and new turn-back facilities provided to allow trains to terminate there while later phases would have added additional stations and the infrastructure upgrades provided elsewhere on the line[16] to provide a half-hourly frequency.[14] However, in August 2020, it was reported that these four proposed phases might be merged into a single one.[17]
The North East Joint Transport Committee's bid for £377 million of funding from the UK Government's £1.28 billion Transforming Cities Fund, submitted on 20 June 2019, includes £99 million to fund the reintroduction of passenger services between Newcastle and Ashington,[18] while further work is ongoing to secure additional public and private investment for the project.[19]
The Department for Transport allocated an initial grant of £1.5 million towards the project costs in January 2020[20] which was supplemented by an allocation of £10 million of funds from Northumberland County Council the following month.[14] This funding enabled AECOM to begin detailed on-site ground investigation works in October 2020.[21] The allocation of a further £34 million of UK Government funding for the project in January 2021 enables the necessary land to be purchased, detailed designs to be prepared and some early preparatory and site works to begin.[22] In January 2021, it was anticipated that the UK Government would fund the remainder of the project cost, estimated at £166 million as of January 2021, once the final phase of design works were completed.[23] However, in April 2021, it was reported that government officials were seeking to reduce the cost of the project as part of the Department for Transport'sProject SPEED initiative.[24] It was reported that the cost-saving measures under consideration included and cutting initial service frequencies from two to one trains per hour and dropping the proposed Blyth Bebside station from initial project scope[24] (although the latter option was later publicly ruled out by Minister for RailwaysChris Heaton-Harris).[25]
A planning application for the new station was submitted to Northumberland County Council on 3 February 2021.[26] The submitted planning documents indicate that the station will have a single 100 m (110 yd) bay platform,[27] located on a short siding[28] which will be recessed into part of the original down (northbound) platform (requiring its partial demolition).[29] It will be accessible from the adjacent Station Yard Car Park (to be expanded to a capacity of 275 cars) and will be linked to the existing Wansbeck Square Footbridge, via a new lift, to provide access to the eastern side of the through lines.[27]
Northumberland County Council submitted a Transport and Works Act Order application to the Secretary of State for TransportGrant Shapps on 26 May 2021,[30][31] which was approved on 27 June 2022.[32] The council has been conferred certain additional powers deemed necessary for the new stations to be constructed and the line upgraded to carry regular passenger services.[33] The new Ashington station will be constructed by the project's primary construction contractor, Morgan Sindall.[34] The main construction phase began in autumn 2022, enabling an opening date in 2024.[34]
Construction of the new station and car park is now completed and is expected to be ready in time for the line opening in December 2024. [35]
Weekday and Saturday daytime services are expected to operate twice-hourly, with an hourly service during the evening and on Sunday, with an end-to-end journey time between Newcastle and Ashington of around 35 minutes.[36] All services are expected to be operated by Northern Trains.
^ abHealey, Alannah; Gillan, Peter (23 February 2021). "21/00387/CCD - PLANNING STATEMENT"(PDF). Northumberland County Council. Retrieved 15 March 2021.
Jowett, Alan (March 1989). Jowett's Railway Atlas of Great Britain and Ireland: From Pre-Grouping to the Present Day (1st ed.). Sparkford: Patrick Stephens Ltd. ISBN978-1-85260-086-0. OCLC22311137.
Jowett, Alan (2000). Jowett's Nationalised Railway Atlas (1st ed.). Penryn, Cornwall: Atlantic Transport Publishers. ISBN978-0-906899-99-1. OCLC228266687.